Collin County's new health care building, medical examiner's office and the medical and mental health wing at its jail have all reached substantial completion, according to a construction update going to the Commissioners Court on Monday, Nov. 16.
The presentation from Sandeep Kathuria, the county's director of building projects, also lays out an estimated $4.7 million plan to nearly double the number of dogs the county animal shelter can house.
Buildings that are finished
The health care, medical examiner and parking garage project, built by the Christman Company, includes a 90,128-square-foot health care building, a 20,318-square-foot medical examiner's office and a 447-space garage. The update lists construction costs, with change orders, at $65.27 million plus $7.7 million for design.
The medical examiner's office and garage reached substantial completion Sept. 30 and the health care building Oct. 13, with punch-list work still under way.
At the jail, the 213,142-square-foot second phase, a medical and mental health addition built by Sedalco, received a temporary certificate of occupancy Sept. 21 and approval from the Texas Commission on Jail Standards Oct. 1. Its construction cost with change orders stands at $113.04 million.
The county's new modular central utility plant, a $31.84 million job built by Sedalco, reached substantial completion Nov. 4.