Custer Road water main job now targeted to wrap up May 1, four months later than planned, as water district briefs council Monday

The North Texas Municipal Water District's Friday update pushes finishing work into 2027, puts the final tie-in at the city's Custer pump station the week of Nov. 30 and says Custer paving should be done by late January.

Dana Keller· AI-assisted, edited by Jake Team

October 23, 20262 min read

Civic Water Infrastructure - illustration, Jake Team LLC

The North Texas Municipal Water District's replacement of the big water line under Custer Road is now expected to run into next spring.

In a project update posted Friday, Oct. 23, the district put the target completion date at May 1, 2027. Its Oct. 9 update had listed Dec. 25, 2026. The district says the schedule is under review because more paving restoration is needed than the contract originally covered.

District staff are listed to give a 30-minute status report on the Custer Road water main at the City Council's preliminary open meeting, which starts at 5 p.m. Monday, Oct. 26.

Where the work stands

According to the update, crews have laid 9,050 of the project's 9,100 feet of pipe, and the bore beneath the President George Bush Turnpike, beside its northbound lanes, is done. Grouting and backfill are finished inside Plano's city limits, and crews have completed paving through Pitman and Dolphin and moved on to Custer Road.

Crews began the permanent Custer paving at Plano Parkway, working in the right lane, and are heading north toward Dolphin Drive. Side streets and alleys from The Hope Center up to Westridge Drive will be shut for short stretches, one after another, as the fresh concrete cures.

The district now expects all three northbound lanes of Custer to have permanent concrete by the end of January 2027, if the weather cooperates, a month later than the end-of-December estimate in its previous update.

The district says it has handed out door hangers to homes whose trash pickup will be affected, and temporary signs with pickup instructions will move along with the crews.

What comes next

The update lists these steps for November:

  • Irrigation, sod and landscaping work beginning the week of Nov. 2.
  • Disinfection testing of the full line the week of Nov. 9.
  • A shutdown of the city's Custer Pump Station for the final tie-in, now scheduled for the week of Nov. 30.

Later phases have no dates yet. They include more potholing on Carmel Drive with a street closure and detour, a separate shutdown of Carmel from Custer Road to Delmonte Circle, a lane closure on the outer southbound lane of Custer, and work to abandon an old 30-inch line that may need more traffic control on Custer.

Questions about the project go to the district at projects@ntmwd.com.

Sources

engage.zencity.io

engage.zencity.io

plano.legistar1.com

plano.legistar1.com

Share

Dana Keller· AI-assisted, edited by Jake Team

Dana Keller covers Plano city hall, the council, and county government.

Related Stories

More in Texas