Worn streets and a broken storm pipe add $223,221 to the Los Rios and Ranch Estates water line job

A second change order on Monday's consent agenda would lift KIK Underground's contract to $4.16 million, while the Dallas North Trunk sewer project is set to come in $198,692 under.

Lena Zimmer· AI-assisted, edited by Jake Team

November 20, 20262 min read

Plano City Council Meeting - illustration, Jake Team LLC

The project replacing aging water lines in the Los Rios Addition and Ranch Estates neighborhoods would cost $223,221 more under a change order on the Plano City Council's consent agenda Monday, Nov. 23.

The increase would bring KIK Underground's contract to $4,155,750. The council awarded the job in September 2025 for about $3.89 million, and city staff approved a first change order of nearly $40,000 for pavement restoration in May, according to an engineering department memo.

This second change order settles the project's final quantities, the memo says. It covers new paving where crews found roads in poor condition, along with the sidewalks, barrier-free ramps and storm inlet tops that go with them. Engineers say the deteriorating pavement has to be replaced so the new paving ties in properly with the existing street.

The order also pays to replace a damaged storm sewer pipe that crews found while laying water line across Country Club Drive, and to install extra water meters because of conditions at the site.

If the council does not approve it, the memo warns, the pavement will keep breaking down, which could mean higher maintenance costs and traffic problems for residents. The money comes from the city's 2026-27 street improvement and water capital budgets, and about $143,833 would remain for future spending.

A sewer project that shrank

A few lines down, the consent agenda goes the other way. A $198,692 reduction would bring S. J. Louis Construction's contract for Phase 2 of the Dallas North Trunk sewer improvements to $16,105,171.

The council awarded that job in May 2025 for about $16.14 million, and staff has since approved six smaller change orders, most of them tied to water lines in the way of construction. The seventh reroutes a wastewater connection around unmapped franchise utility lines, which cuts the amount of pipe and the number of manholes needed.

Crews also hit stable rock at shallower depths than expected, so the piers for the line's aerial crossings do not need to go as deep, the memo says. Approving the decrease returns the unused money to the city for other sewer projects.

Consent items are usually approved together in a single vote. The council meets at 7 p.m. at the Plano Municipal Center, 1520 K Ave.

Sources

plano.legistar1.com

plano.legistar1.com

Share

Lena Zimmer· AI-assisted, edited by Jake Team

Lena Zimmer covers weather, storms, and seasonal life around Plano.

Related Stories

More in Texas