The project replacing aging water lines in the Los Rios Addition and Ranch Estates neighborhoods would cost $223,221 more under a change order on the Plano City Council's consent agenda Monday, Nov. 23.
The increase would bring KIK Underground's contract to $4,155,750. The council awarded the job in September 2025 for about $3.89 million, and city staff approved a first change order of nearly $40,000 for pavement restoration in May, according to an engineering department memo.
This second change order settles the project's final quantities, the memo says. It covers new paving where crews found roads in poor condition, along with the sidewalks, barrier-free ramps and storm inlet tops that go with them. Engineers say the deteriorating pavement has to be replaced so the new paving ties in properly with the existing street.
The order also pays to replace a damaged storm sewer pipe that crews found while laying water line across Country Club Drive, and to install extra water meters because of conditions at the site.
If the council does not approve it, the memo warns, the pavement will keep breaking down, which could mean higher maintenance costs and traffic problems for residents. The money comes from the city's 2026-27 street improvement and water capital budgets, and about $143,833 would remain for future spending.
A sewer project that shrank
A few lines down, the consent agenda goes the other way. A $198,692 reduction would bring S. J. Louis Construction's contract for Phase 2 of the Dallas North Trunk sewer improvements to $16,105,171.